| 1 |
Earthwork in excavation(in Mass) in any kind of soil including hard soil, slushy muck, hard moorum soil with the help of crawler mounted Excavator like Poclain / Tata Hitachi up to a depth of 3.00 Metre from the existing bed level for digging of pond, Trench cum bund (TCB)and Field bunding (FB) & disposing/ removing the excavated spoil on the bund (Spoil-bank) as per direction and upto a dist. of 1000.00 Metre, with the help of required dumpers. Rate should include for excavation by Mechanical excavator & disposing the excavated spoil by Dumpers, Marching time of Mechanical equipments.
|
|
|
|
|
|
|
Excavation for pond
|
|
|
|
|
|
| 2 |
Fine Dressing & Levelling of the excavated spoil on bund (spoil-bank) with the help of Mechanical excavator for proper compaction & finally by manual labour as per direction. Rate should include the earth cutting & filling to suit the site requirement
|
|
|
|
|
|
| 3 |
Outlet work – Supplying & laying NP2 RCC spun pipe 300mm dia with collar in lines and level and providing approved jointing materials and joint properly as per direction of E/I
|
|
|
|
@php
$amount = ($qc->outlet_work_payable_quantity ?? 0) * ($rateSheet['outlet_hume_pipe'] ?? 0);
@endphp
|
|
| 4 |
Supplying, constructing random rubble masonry work using trap stone boulders of 200–300 mm size in cement sand mortar (1:6) in foundations, superstructure, manholes, ducts, drains etc., including fair cutting, waste, bonding, plumbing, lining, levelling, flushing, raking joints, scaffolding and curing, all as per drawings, specifications, and directions of the Engineer/ Consultant. Includes all materials, tools, plant and labour complete in all respects.
|
|
|
|
|
|
| 5 |
Silt trap earthwork in excavation |
|
|
|
@php
$amount = ($rateSheet['inlet_earthwork'] ?? 0) * ($qc->outlet_work_payable_quantity ?? 0);
@endphp
|
|
| 6 |
Inlet Pitching Work – Earthwork excavation in ordinary soil, dressing of soil as per direction of E/I.
|
|
|
|
|
|
| 7 |
Inlet Stone Pitching – Supplying and laying (properly as per design and drawing) rip-rap with good quality of dry boulders (200–300 mm size), including cost of materials, royalty, taxes etc., excluding carriage, as per specification and direction of E/I.
|
|
|
|
|
|
| 8 |
Display Board (1m × 1m × 0.3m) |
|
|
| 8.A |
Earth work in excavation |
|
|
|
|
|
| 8.B |
Supplying, constructing one or more brick thick burnt clay brickwork (Foundation and Superstructure)
|
|
|
|
|
|
| 8.C |
Supplying and laying plaster with (1:6) cement sand mortar at all heights and depths, above and below finished ground level, to faces of walls, pillars, columns – 12 mm thick (in one operation)
|
|
|
|
|
|
| 8.D |
Wall writing with synthetic paint as per guidance of site in-charge
|
|
|
|
|
|